When building owners and managers hear the
word asbestos, heads turn, and often times heads turn the
other way. Asbestos has come to be a troublesome thing
that often carries a hefty price tag, but it is not
something that can be ignored.
What is Asbestos?
Asbestos was widely used in building
materials primarily from the 1950’s through the 1970’s.
Asbestos quickly became popular in roofing due to it’s fire
resisting properties as well as its resistance to aging.
The low oxidation and rotting process of asbestos containing
roofing felts made for long lasting built-up roofs and
increasing popularity of asbestos felt use.
These felts contain chrysotile asbestos fibers that are
natural fibers obtained from crushing and refining
chrysotile ore. ASTM specification D250 required that
the dry felt must contain a minimum of 85% asbestos.
Other roofing materials, such as mastics, coatings, transite
panels, and shingles were also manufactured with the use of
asbestos.
The fibers are small serpentine fibers that
can become airborne for long periods of time, making them
easily inhaled by humans. These fibers, once in the
lungs, stay in the lungs. Asbestosis, mesothelioma and
cancers of the lung, esophagus and stomach are deadly
diseases that are a result of an accumulative dose of
asbestos. In the early 1980’s, this danger set into
action the Asbestos Hazard Emergency Response Act (AHERA)
requiring that K-12 schools in the U.S. develop a management
plan for dealing with any and all asbestos containing
building materials. The Occupational Safety and Health
Administration (OSHA) and the Environmental Protection
Agency (EPA) also set their own regulations for dealing with
asbestos. OSHA set a standard that occupational
exposure to asbestos should not be more then 0.2 fibers per
cubic centimeter of air longer than 5 micrometers in length.
EPA controls the removal and/or disposal of asbestos
containing building materials under the National Emission
Standards for Hazardous Air Pollutants (NESHAP). Local
governing authorities may also have their own removal and/or
disposal requirements, which might be totally different from
OSHA or the EPA. Prior to any asbestos removal
project, check with the local governments so their
requirements can be met.
Removal Requirements
OSHA has regulated the removal of asbestos
containing roofing materials for a long time. Removal of
roofing felts, shingles and transite panels are so-called
Class II work, and removal of mastics and coatings are
so-called incidental work. Some of the early
requirements for removal of asbestos-containing roofing
materials included proper worker training, air monitoring,
protective clothing, respiratory protection, and wet/dry
cleaning. In 1994, a revision by OSHA imposed more
stringent removal requirements for asbestos containing roof
removal, regardless of exposure level.
These strict requirements have been protested
by the roofing industry saying that the asbestos in roofing
is not friable, that the asbestos is encapsulated, and that
the asbestos fiber release is little to none. The
National Roofing Contractors Association (NRCA) took on
OSHA, saying that most asbestos containing roofing materials
posed very little to no health hazard, as they are
considered non-friable. In 1995, OSHA and the NRCA
reached an agreement on a relaxed set of procedures for
Class II work and incidental work. This agreement
still requires air monitoring, respiratory protection,
protective clothing and proper cleaning. However,
these practices are not required if an exposure assessment
is determined to be below the Permissible Exposure Limit
(PEL).
The assessment is to be based on air
monitoring results collected by the contractor on like jobs
over the previous 12 months, air monitoring results
collected by the NRCA, or air monitoring results collected
during the start of the project. However, if the air
monitoring is to be done on the job, all requirements, such
as for personnel protection and cleaning must be followed
until the results are found to be below the PEL.
Intact roofing materials are considered
non-friable and removal of such materials must remain
non-friable or the job will fall back in to the stringent
removal requirements set by OSHA. The roofing
materials must be removed without the use of power tools
such as a roof cutter. If the contractor decides to
use power tools for the removal of, lets say, the roofing
felts, then the roof cutter must be equipped with a sprayer
to put a mist of water on the roofing at the cutter blade.
As the roof is cut, the felts become friable and the mist of
water is needed to settle any dust and fiber release.
The cut area should then be vacuumed with High Efficiency
Particulate Air filters. Dry removal is allowed with
the proper notification and approval of the EPA.
Summary
As a building owner or manager, faced with an
upcoming roof removal project, you must first test the roof
to determine the presence of asbestos. The field
membrane, as well as the flashings, need to be tested.
In many cases, flashings were installed using asbestos felts
but the field was not. Therefore, it is important that
both the field membrane and flashings be tested. An
approximately 3” x 3” sample of the field and flashings is
usually large enough for testing. The membrane samples
should then be labeled as membrane type, location and
project reference, and be sent to a National Institute of
Occupational Safety and Health accredited asbestos testing
laboratory to determine if the roofing materials contain
asbestos. The laboratory will return a report with the
test results. This report should be kept in the
project file for any future reference. Prior to
collecting the roof samples to be tested, check with local
governments to see if there are any requirements that the
person collecting the samples must meet. Some local
governments require the person collecting the samples to be
trained and certified in asbestos removal.
If the field membrane and/or flashings test
positive for asbestos, it is then time to take a level
headed, common sense approach. Select a core group of
contractors trained in asbestos removal and familiar with
notifying and dealing with OSHA, the EPA, and even the DOT.
Contact local governments to obtain their requirements.
Discuss with the selected contractor their removal process,
including personnel and environmental protection.
Obtain the projects exposure assessment and/or on the job
air monitoring results. Require that the asbestos
containing materials are disposed of at an EPA approved
landfill and that the contractor follows all requirements of
the landfill and obtain all manifests. Lastly, keep
very good, step-by-step records and keep all records in the
project file just in case they are needed in the future.
Remember, even though the roof has been properly removed and
disposed of in an EPA approved landfill, you still own and
are responsible for the asbestos containing materials.